Complete setup process — from unboxing to live displacement monitoring.
Check everything is present and undamaged before heading to site.
Set up your monitoring project before going to site.
Install the app on your phone before going to site.
The sensor must be installed rigidly — any translational movement invalidates measurements.
Mount prisms firmly on the structures you want to monitor.
Power up the sensor and shield using the supplied cable set.
Do not extend power cables beyond 3 m. Longer cables may cause voltage drop and unstable operation.
Pair your phone via Bluetooth, then switch to the sensor's WiFi network.
Set up your project on the platform first. Your device needs to sit in a project with no baseline configured before the wizard will start.
The baseline is the reference point for all future displacement measurements.
Required only if you need relative displacement measurements between two targets.
Set thresholds early.
Confirm the system is healthy and data is flowing before closing out the installation.
Once data quality checks pass, your TotaLite system is live — continuously watching your structure and alerting only when it matters.