Phase 1

Preparation

1

Unbox & verify components

Check everything is present and undamaged before heading to site.

  • TotaLite Sensor + Shield
  • AC/DC Power Adapter (12V, 1.5A)
  • Power Splitter Cable
2

Create a project in the TotaLite Platform

Set up your monitoring project before going to site.

  • Obtain login credentials from the TotaLite team
  • Log in at app.totalite.io
  • Create a new project and assign your sensor to it
Reference: TotaLite Platform
3

Download the TotaLite Mobile App

Install the app on your phone before going to site.

  • Android: Download via Firebase App Distribution
  • iOS: Install TestFlight first, then join via TestFlight link
Reference: TotaLite App
Phase 2

Hardware installation

4

Mount the TotaLite Sensor

The sensor must be installed rigidly — any translational movement invalidates measurements.

  • Use the TotaLite Bracket for poles 50–60 mm (U-bolts; 4× M6 bolts, max 20 mm)
  • Minimise vibration and ensure zero flex in the mounting
Reference: Sensor Installation
5

Install survey prisms

Mount prisms firmly on the structures you want to monitor.

  • Minimum angular separation: 2° between targets
  • At 10 m → targets ≥ 0.35 m apart  |  At 50 m → ≥ 1.75 m apart
  • Drill into concrete for a stable, permanent connection
  • Face the prism center toward the TotaLite sensor
  • Max range: 70 m
  • Record the slope distance from each prism to the sensor lens — you'll need these later
Reference: Prism Installation
6

Connect power

Power up the sensor and shield using the supplied cable set.

  • Use the provided 12V adapter and power splitter cable
  • Connect both the sensor and shield M12 connectors at the back of the device
  • Accepted input: 9.5–24V DC, minimum 18W
  • Confirm status via LED indicators on the sensor

Do not extend power cables beyond 3 m. Longer cables may cause voltage drop and unstable operation.

Reference: Power Supply
Phase 3

Sensor configuration

7

Connect the mobile app to the sensor

Pair your phone via Bluetooth, then switch to the sensor's WiFi network.

  • Open TotaLite app → tap Connect
  • Bluetooth pairing code: 123789
  • Enable sensor WiFi from within the app
  • Switch your phone's WiFi to the sensor network
  • Disconnect from the sensor WiFi once configuration is complete
Reference: Connect App
8

Configure app wizard

Set up your project on the platform first. Your device needs to sit in a project with no baseline configured before the wizard will start.

  • Budget 20 minutes on site. The wizard walks you through mounting, power, and target scanning — keep the line of sight clear during measurement.
  • Check target separation before you leave. Targets flagged too close together need to be moved and re-measured, or excluded.
  • Record slope distances on site. You'll need them for baseline setup back on the platform — that's where the installation actually finishes.
Reference: Setting-up
Phase 4

System setup

9

Create a baseline in the platform

The baseline is the reference point for all future displacement measurements.

  • Go to your project → click Create Baseline
  • Select the date/time for the baseline measurement
  • Name each target and enter its slope distance (sensor lens to prism center)
  • Mark 1 reference target for yaw compensation
  • Mark a 2nd reference target only if the sensor tilt (pitch/roll) exceeds 20°
Reference: Create the Baseline
10

Set up target pairs (optional)

Required only if you need relative displacement measurements between two targets.

  • In the platform, drag a line between two targets to create a pair
  • Skip this step if only absolute displacement data is needed
Reference: Create the Baseline › Target Pairs Setup
11

Set up threshold alerts

Set thresholds early.

  • Click Set Alerts on a displacement chart, and enter a value per target (1 mm–499 mm). Monitoring starts from that moment — nothing is backdated.
  • Thresholds cover both directions. A 3 mm threshold alerts on displacement past +3 mm or −3 mm.
  • Alerts trigger after 1 hour past threshold. You'll get a notification, and admins get an email.
  • Check the 90-day status bar regularly. Green means no alerts; red means review it — click through to see which target, and when.
Reference: Alerts
12

Final verification & quality check

Confirm the system is healthy and data is flowing before closing out the installation.

  • Confirm data connectivity: LTE or Ethernet active
  • Verify that measurements are appearing in the platform
  • Review data quality metrics: CQF > 70% and SNR > 18 dB
  • Contact the TotaLite team for a baseline quality assessment
Reference: Advanced › Data Quality

System ready for monitoring